Alde
and ore Consultation
We welcome your comments and thoughts
on the proposed shortlisted options described on this website
and associated
consultation document through the online
questionnaire. In particular, we would like your feedback
on the following:
- Are there any shortlisted
options , that you would consider unacceptable? If so,
please state why.
- Of the proposed shortlisted sites for managed realignment,
are there any sites that you would find unacceptable? If
so, please state why.
- Are there any further options that you believe should
be shortlisted? If so, please state why.
Any further comments on the shortlisting process and the proposed
shortlisted options are also welcome. What
is the approach to the Alde and Ore estuary strategy study?
The Alde and Ore estuary is the second of the Suffolk Estuarine
Strategies studies to be undertaken. Consultation with organisations
and individuals who are interested and/or affected by the proposed
strategy will be undertaken at key stages throughout the programme,
as shown in Table 1. |
|
| HAVE
YOUR SAY |
| To comment on the development
of the strategy online, click here |
|
Table 1: Outline of the consultation process
| Stage
of the Programme |
Consultation
Opportunity |
Timescale |
| Introduction
to the Alde and Ore estuary study |
Initial
consultation with the local community, landowners, statutory
authorities and other parties. |
COMPLETED |
| Initial
appraisal of options for the Alde and Ore estuary |
Presentation
of the various flood managment options that could be used in
the strategy in the form of a public consultation document.
Consultation with organisations and individuals who expressed
an interest in response to the previous consultation. |
COMPLETED |
| Shortlisting
of options for the Alde and Ore estuary |
Presentation
of the short listing of Estuary Options in the form of a public
consultation document and public exhibition. Consultation with
organisations and individuals who expressed an interest in response
to the previous consultation document. |
Winter
2004/5 - current round of consultation |
| Appraisal
of preferred option for the Alde and Ore estuary |
Presentation
of the preferred option in the form of a public consultation
document and public exhibition. Consultation with organisations
and individuals who expressed an interest in response to the
previous consultation document. |
Summer
2005 |
| Publication
of Alde and Ore estuary strategy |
Advertisement
in local newspapers.
Report available for public comment.
|
Summer
2005 |
| Approval
of Alde and Ore estuary strategy |
Period
for review of strategy by DEFRA and other statutory consultees. |
From
Summer 2005 |
| Alde
and Ore estuary strategy implementation |
Implementation
of the Alde and Ore estuary strategy findings and recommendations. |
Following
approvals |
The results of this continuing consultation process will be used in
the selection of a preferred strategy. Organisations and individuals
that have expressed an interest at this stage will again be consulted
on the final preferred strategy. A Strategy Report including the findings
of the technical and economic appraisals and the Strategic Environmental
Assessment will then be published following the confirmation of the
preferred strategy. Approval of the Strategy will then be sought from
Defra, statutory consultees and the wider Alde and Ore estuary community
before implementation of the Strategies findings can be carried out.
Have Your Say
If you wish to register an interest or comment on the development
of the Suffolk Estuarine Flood Management Strategies, and in particular
the Alde and Ore strategy online, click here.
Click
here to print out a blank copy of the comment form (PDF format)
which you can complete by hand.
Summary of Consultation Responses to
Date
Click here
to review a summary of the responses received from the shortlisting
stage of consultation on the Alde and Ore Estuary Strategy
Click here
to review a summary of the responses received from the 'Introduction'
& 'O2ptions' rounds of consultation on the Alde and Ore Estuary
Strategy.
The
Strategy Consultation Groups
Two consultation groups have been set up to aide the development of
the strategy for the Alde and Ore:
The Suffolk Estuarine Strategies Consultation Group
An overarching consultation group for the Blyth, Alde and Ore and
Deben estuaries has been set up to provide guidance on the requirements
of UK law, local government policy, planning issues and initiatives
in the region and provide comment on project objectives for the Strategy.
The group is made up of representatives of the District and County
Councils, English Heritage, English Nature, the National Farmers Union,
Royal Yachting Association and the Suffolk Coast and Heaths Management
Unit.
The Alde and Ore Strategy Consultation Group
A consultation group made of representatives of the local community
has also been set up in conjunction with the Alde & Ore Estuary
Planning Partnership (EPP). The Consultation Group will provide guidance
and information on and about local issues and provide comment on local
objectives to be considered in the development of the strategy. The
Alde and Ore Consultation Group consists of key stakeholders from
the EPP which include; Suffolk Coasts and Heaths Unit, the Environment
Agency, The National Trust and English Nature, Aldeburgh Town Council,
New Orford Town Trust and the Alde and Ore Association, sailing, business
and farming interests and many other groups such as wildfowlers, fishermen,
the RSPB, Suffolk Preservation Society etc. and individual residents.
The Strategy will contribute towards the production of the overall
Estuary Management Plan currently being undertaken by the EPP. More
information about the Alde and Ore Estuary Planning Partnership can
be found at http://www.aldeandore.net.
|