Option 1: No Active
Intervention throughout the Estuary
This option would involve ceasing all maintenance, repair and
renewal work on the defences throughout the Blyth Estuary. The
defences would continue to be monitored and assessed until they
eventually failed or a “Do Something” option was
deemed necessary. Areas of land currently protected from tidal
flooding would no longer be protected. Figure 1 shows the area
over which high spring tide water levels would extend under
this option. |

Figure 1 |
Option 2: Hold the Line throughout the Estuary
This option would involve maintaining the existing flood defences
on their current alignment throughout the estuary. The change
that this option would have on the low and high tides is shown
in Figure 2. The low and high tide levels under Option 2 are
similar to the current low and high tide levels in the Estuary.
|

Figure 2 |
Option 3: No Active Intervention/Managed Realignment Upstream
of the Harbour Mouth + Hold the Line of the Harbour Mouth
This option would involve undertaking work on the present harbour
arms at the mouth of the estuary (excluding the present Harbour
wall upstream). Elsewhere in the estuary No Active Intervention
would be applied as in Option 1. The change that this option
would have on the low and high tides is shown in Figure 3.
|

Figure 3 |
Option 4: No Active Intervention/Managed Realignment at Robinson
Marshes + Hold the Line elsewhere
This option would involve an option of No Active Intervention
at the stretch of defence that protects Robinson Marshes from
flooding and maintaining the defences on their current alignment
elsewhere in the estuary. The change that this option would
have on the low and high tides is shown in Figure 4.
|

Figure 4 |
Options 5a and 5b: Advance the Line by Narrowing the Estuary
or Making the Estuary Shallower at the Bailey Bridge + Hold
the Line elsewhere
Options 5a and 5b would involve either narrowing the channel
or raising the bed of the estuary at the Bailey Footbridge upstream
of the present harbour moorings and maintaining the defences
on their current alignment elsewhere in the estuary. The change
that these options would have on the low and high tides is shown
in Figure 5.
|

Figure 5 |
Options 6a and 6b: Advance the Line by Narrowing the Estuary
or Making the Estuary Shallower at the Bailey Bridge + No Active
Intervention/Managed Realignment at Tinkers Marshes + Hold the
Line elsewhere
Options 6a and 6b would involve either narrowing the channel
or raising the bed of the estuary at the Bailey Bridge in combination
with either No Active Intervention or Managed Realignment at
Tinkers Marshes and maintaining the defences on their current
alignment elsewhere in the estuary. The change that these options
would have is shown in Figure 6 |

Figure 6 |